The Nemmadi value-add — made visible

What we find that a normal walk-through misses.

Real findings from RWA audits, anonymised to protect builders. Every defect, photo, and code reference is exactly as recorded on site. Every consequence is what we’ve watched MCs face when these were missed.

Finding 01 · Gas Bank · Detection Project F · pg 35 · photo 28
Audit photo — Project F · pg 35 · photo 28
Project F · pg 35 · photo 28
critical NBC 2016 Part 9
Gas Bank

Gas leakage detection system — switched off.

Gas leakage detection system kept off. Maintenance report not provided by AMC vendor and periodic inspection checklist not maintained.

If missed

With detection disabled, a slow leak goes unnoticed until a resident smells gas — or until something ignites it. NBC 2016 Part 9 expects continuous monitoring at the gas bank precisely because LPG vapour pools at floor level and a single ignition source is enough for an explosion. A switched-off panel is a code violation hiding inside a green-light room.

Three findings, three categories of failure.

§ 02 · Lifts · Electrical · Fire
Audit photo — Project D · pg 97
Project D · pg 97
critical
Lifts & ELV

Lift ARD failure — passengers can be trapped on a power cut.

ARD not working.

If missed

ARD (Automatic Rescue Device) is the battery backup that walks the lift to the nearest landing when grid power drops, then opens the doors. Without it, occupants are stuck inside the car between floors until a technician arrives — minutes in the best case, hours in the worst. Children, elderly residents and anyone with claustrophobia bear the brunt.

Audit photo — Project C · pg 17
Project C · pg 17
critical IS 3043
Electrical

Earth strip lap joints — the safety system that exists only on paper.

Earth strip lap joints have not been executed properly, and joints are missing at certain locations.

If missed

IS 3043 requires earthing strip joints to overlap by twice the strip width and be secured with at least two bolts, nuts and spring washers. Short overlaps and open joints raise earth resistance — when an appliance shorts, fault current has nowhere to go and the metal body of the panel, the lift, or the streetlight pole becomes live. Touching it is fatal.

Audit photo — Project D · pg 46
Project D · pg 46
critical NBC 2016 Part 4; IS 12459
Fire-fighting

Fire-stop slab missing — compartmentation is gone.

Fire stop slab not provided.

If missed

Without floor-level fire-stops in service shafts, a fire on a lower floor sends smoke and flame straight up the shaft to every floor above. Compartmentation — the principle that lets one floor burn while others stay safe — is gone.

By trade — the full picture.

§ 03 · 31 findings across 6 trades
Trade filter
Audit photo — Project B · pg 8
Project B · pg 8
critical
Electrical

Transformer silica gel turning pink — moisture leaking in.

Transformer silica gel observed turning pink, indicating moisture saturation; periodical maintenance / replacement pending.

If missed

The breather's silica gel keeps moisture out of the transformer oil. Once it saturates (blue → pink), water enters the oil, dielectric strength drops, and the insulation ages fast. The end of that road is a transformer fault that takes the whole community offline.

Audit photo — Project H · pg 23
Project H · pg 23
critical
Electrical

Live terminal exposed inside a distribution board.

Live terminal found exposed inside the distribution board (DB).

If missed

A DB door is the last barrier between a maintenance technician's hand and 230V. An exposed live terminal turns routine work into a shock hazard, and a stray screwdriver tip into an arc flash.

Audit photo — Project G · pg 21
Project G · pg 21
critical
Electrical

MCB rating mismatched against sanctioned load.

Multiple breaker rating mismatches against sanctioned 3 BHK loads — 16A on 5 kW (needs 20A); 25A on 5 kW (needs 20A); 32A on 5 kW (needs 20A); 10A on 1 kW DG backup (needs 6A).

If missed

Undersized breakers nuisance-trip on normal load; oversized breakers let cables run hot before tripping. The oversized case is the dangerous one — wires inside the wall heat up, insulation degrades, and a fire starts behind the drywall before any breaker notices.

Audit photo — Project D · pg 106
Project D · pg 106
critical
Electrical

Earth fault relay not configured at the transformer yard.

EFR (Earth Fault Relay) trip value/settings not set (relay left at default/unconfigured). Earth fault protection not commissioned.

If missed

An EFR sitting at factory defaults will not trip when it should. Fault currents that should clear in milliseconds keep flowing — long enough to start a cable fire or hold a person in contact with a live surface.

Audit photo — Project A · pg 22
Project A · pg 22
critical
Fire-fighting

Fire alarm panel kept switched off.

Fire alarm panel kept in OFF condition; suggested to keep it always in ON condition.

If missed

A panel left off does not detect smoke, does not sound alarms, and does not trigger evacuation messages. Residents only learn there is a fire when they smell it. Floor-by-floor evacuation, designed to take minutes, instead happens in panic.

Audit photo — Project G · pg 51
Project G · pg 51
critical
Fire-fighting

Fire pumps left in manual mode.

Fire pumps are kept in manual mode. Needs to be kept in auto mode always.

If missed

In auto mode the pumps start the moment hydrant pressure drops, which is the moment a hose is opened or a sprinkler activates. In manual mode, someone has to physically reach the pump room and press a button — during a fire, in smoke, while everything else is happening.

Audit photo — Project H · pg 37
Project H · pg 37
critical
Fire-fighting

Fire brigade inlet blocked by parked cars.

Access to the fire brigade inlet is blocked by parked vehicles, and the driveway is obstructed by barricades.

If missed

The brigade inlet is how the fire department pumps water into the building's standpipe. If their truck cannot reach it, internal hydrants and sprinklers stay dry. Towing a car takes ten minutes the building does not have.

Audit photo — Project D · pg 38
Project D · pg 38
critical
Fire-fighting

Fire-shaft door padlocked with a regular key.

Fire shaft door found locked using lock & key; fire shaft door found without designated emergency access key/means of opening.

If missed

Fire shafts are designed for instant access — break-glass keys, captive keys, or no lock at all. A normal padlock means whoever has the key has to be located, woken, and brought to the shaft before firefighting can begin. The fire does not wait.

Audit photo — Project F · pg 38
Project F · pg 38
critical
Fire-fighting

Wet riser valve closed across all towers.

All wet riser valves were kept in closed condition.

If missed

A wet riser carries water up the building under pressure so firefighters can connect a hose at any floor. With the valve closed at the base, all the floor outlets are dry. Crews arriving at floor 18 find an empty pipe.

Audit photo — Project D · pg 46
Project D · pg 46
critical NBC 2016 Part 4; IS 12459
Fire-fighting

Fire-stop slab missing at electrical shafts.

Fire stop slab not provided.

If missed

Without floor-level fire-stops in service shafts, a fire on a lower floor sends smoke and flame straight up the shaft to every floor above. Compartmentation — the principle that lets one floor burn while others stay safe — is gone.

Audit photo — Project D · pg 39
Project D · pg 39
critical
Fire-fighting

Fire-staircase exits into the basement.

Fire staircase exits directly into the basement instead of leading to a safe, open area at ground level.

If missed

A fire escape must end where you are safe — outside, at ground level. Discharging into the basement means evacuees walk straight into the smoke layer they just escaped, and toward a level where firefighters cannot easily reach them.

Audit photo — Project D · pg 55
Project D · pg 55
critical
Fire-fighting

FACP dead — fire alarm panel not powering on.

Fire Alarm Control Panel (FACP) not powering ON. Panel remains dead/no display indication; fire alarm system non-operational.

If missed

The FACP is the brain of the entire detection-and-alarm system. With it dead, smoke detectors register nothing, manual call points do nothing, and evacuation announcements never play. The building has the parts of a fire alarm but none of the function.

Audit photo — Project D · pg 60
Project D · pg 60
critical LPS design / IEC practice
Gas Bank

LPG line and lightning arrester running together — no separation.

Lightning arrester (LPS air terminal/down conductor) and gas pipeline installed without maintaining the required minimum separation distance.

If missed

A lightning strike sends thousands of amps down the LA conductor. If a gas line runs alongside, the strike can side-flash to it — puncturing the pipe and igniting the contents in the same instant. Required separation exists for exactly this reason.

Audit photo — Project F · pg 34
Project F · pg 34
critical NBC 2016 Part 9, Section 4
Gas Bank

Gas pipeline laid above electrical wiring.

Gap not maintained between gas pipeline and electrical services. All gas pipelines should run below the electrical wiring with a 60 mm clearance.

If missed

NBC requires gas to run below electrical because a leaking gas line wets a cable above it; an electrical fault in that cable then has a fuel source directly under it. The clearance is the difference between a leak and an explosion.

Audit photo — Project F · pg 35
Project F · pg 35
critical
Gas Bank

Gas pipeline at driveway — no barricade.

Barrication not provided for the gas pipeline at the driveway.

If missed

A reversing car or a delivery truck only needs to clip an unprotected pipe once. Bollards or kerb-mounted barriers are the cheap, code-required answer; without them, the LPG main is one fender-bender away from a leak.

Audit photo — Project H · pg 25
Project H · pg 25
critical
Plumbing & WTP

Backwash line cross-connected to recycled water without an NRV.

Water-body filter backwash pipeline is connected to the PDRWP line, creating a possibility of backflow. A Non-Return Valve (NRV) must be installed.

If missed

Filter backwash carries the dirt the filter just trapped. Without a non-return valve, that dirt can flow backward into the recycled-water main during a pressure drop. Once contaminated, the line stays contaminated until it's flushed.

Audit photo — Project G · pg 26
Project G · pg 26
critical
Plumbing & WTP

PRV bypass left half-open.

PRV bypass valve is kept 50 percent in open condition and the pressure gauge is missing near car parking.

If missed

A pressure-reducing valve protects fixtures from main-line pressure that would burst them. Bypassing it sends full pressure to taps and flush tanks meant for low pressure — taps drip, flush valves leak, and a fixture eventually splits.

Audit photo — Project D · pg 16
Project D · pg 16
critical
Plumbing & WTP

Plumbing pipeline running above the UPS and electrical panel.

Plumbing pipeline installed above UPS and electrical panel.

If missed

A water line above live electrical equipment is one joint failure from disaster. A drip into the UPS shorts the battery bank; a leak into the panel triggers a flashover. Both can ignite the room.

Audit photo — Project H · pg 46
Project H · pg 46
critical
Plumbing & WTP

UV disinfection lamp failed in the STP.

UV lamp in the UV disinfection system has failed and must be replaced immediately.

If missed

UV light is what kills pathogens in treated wastewater before it goes back into landscaping or flush systems. A failed lamp means untreated effluent — bacteria, viruses, the lot — flowing to taps that residents and gardeners touch every day.

Audit photo — Project A · pg 12
Project A · pg 12
critical
Lifts & ELV

Lift intercom dead — no two-way contact during entrapment.

Intercom not working in the lifts at all towers; needs to be rectified.

If missed

When someone is trapped in a stalled car, the intercom is the only fast way they speak to the security desk. With it dead, they bang on the doors and hope a neighbour hears. Children, elderly residents, and anyone without a charged phone are most exposed.

Audit photo — Project G · pg 25
Project G · pg 25
critical
Lifts & ELV

CCTV stores only 5 days of footage.

CCTV record storage days provided are only 5 days. Recommended to have 30 days record storage capacity.

If missed

Most disputes — package theft, hit-and-run in the parking, vandalism — are reported a week or more after they happen. Five days of footage means the evidence is already overwritten by the time anyone goes looking.

Audit photo — Project G · pg 57
Project G · pg 57
critical
Lifts & ELV

Lift pit and door rails clogged with debris.

Observed debris inside the pit and car door railing.

If missed

Debris in the pit fouls buffers and limit switches; debris in the door rails jams the doors. Both produce mid-floor stops, mis-levelling and the kind of door re-cycling that traps a passenger and damages the rollers at the same time.

Audit photo — Project A · pg 12
Project A · pg 12
critical
Lifts & ELV

Boom barrier at the exit driveway not working.

Exit boom barrier not working; needs to be rectified.

If missed

The barrier at exit is a deterrent against unauthorised vehicles leaving and a chokepoint where security can verify a car. With it down, anyone can drive in or out — including someone leaving with stolen goods.

critical
Document audit

Fire force clearance certificate not provided.

Fire force clearance certificate (CC) not provided for the Fire Protection System and Fire Alarm & Public Addressing System.

If missed

Without the CC, there is no statutory record that the fire systems were ever inspected and approved. If insurance investigates a future claim or a regulator audits, the building has nothing to show.

critical
Document audit

CEIG drawing approval letter not provided.

Drawing approval letter from CEIG (Chief Electrical Inspectorate to Government) not provided.

If missed

CEIG approval is the legal sign-off on the entire HT/LT electrical installation. Without it, every electrical fault becomes a question of whether the system was approved in the first place.

critical
Document audit

As-built drawings without consultant signature/stamp.

As-built drawings provided without affixing the signature and stamp of the design consultant. Handing-over documents submitted without the builder's signature and stamp.

If missed

An unsigned drawing is not an as-built — it's a draft. The MC inherits a building they cannot trust the drawings of, and any future modification starts with a survey to figure out what's actually in the wall.

critical
Document audit

Testing & commissioning reports not signed.

Testing & commissioning report provided without affixing the signature and stamp of the builder for FPS, FAPS, fire pump pressure-switch calibration and FAPA panel.

If missed

An unsigned commissioning report is not a record of testing — it's a claim. If pumps fail to start during a real fire, there is no signed evidence the sequence was ever proven to work.

critical
Document audit

DBR (Design Basis Report) not provided.

DBR not provided for water supply system, STP, Fire Protection System, Fire Alarm & Public Addressing System, and electrical installation.

If missed

The DBR is the document that states why every system was sized and chosen the way it was. Without it, the MC cannot tell whether a future load increase will overload the transformer or whether the STP is sized for 80% occupancy or 110%.

critical
Document audit

Lift installation clearance certificate not provided.

Lift installation clearance certificate not provided from authority. Lift drawings not provided.

If missed

Lifts run on a statutory licence. A missing clearance certificate is a renewal problem the MC inherits — and a liability problem the day a passenger is hurt.

critical
Document audit

OEM manuals missing for panel breakers, relays and instruments.

OEM Manuals not provided for panel breakers, relays, and instruments.

If missed

Without manuals, the MC's electrician cannot configure trip settings, change relay parameters, or even safely reset a fault. Every visit needs the OEM, every visit costs a service call.

critical
Document audit

Sumps and plant-room equipment layout drawings not provided.

Plant room plumbing & equipment layout not provided. Sumps details not provided. Landscape water supply & drainage layout and Podium water supply layout not provided.

If missed

When a sump pump fails or a plumbing leak appears in the plant room, the maintenance team has nothing to refer to. Diagnosis becomes guesswork; rectification becomes excavation.

§ 04 · Document audit

We don’t just inspect. We check the paperwork.

Most residents don’t know these documents should exist. Without them, future repairs become guesswork — and warranty claims fall through.

01 Fire force clearance certificate (CC) If missing — No statutory proof the fire systems were ever approved — insurance and audit risk.
02 CEIG drawing approval letter If missing — The legal sign-off for the HT/LT installation; every electrical incident becomes a compliance question without it.
03 Signed as-built drawings If missing — Unsigned drawings are drafts. The MC inherits a building it can't trust the layout of.
04 Signed testing & commissioning reports If missing — Without signatures, "tested" is a claim, not a record — no evidence that pumps, alarms or pressure switches were ever proven to work.
05 Design Basis Report (DBR) If missing — The "why" behind every system size and choice. Without it, no MC can plan capacity changes.
06 Lift installation clearance certificate If missing — The statutory licence to operate the lifts. Missing = renewal and liability exposure.
07 OEM manuals for breakers, relays, instruments If missing — Without them, in-house electricians cannot configure or reset protection devices safely.
08 Plant-room and sump layout drawings If missing — Routine breakdowns become excavations. Every diagnosis starts from scratch.

How we add value, step by step.

§ 05
STEP 01

Site walkthrough

Every floor, every common area, every plant room.

STEP 02

Document review

Against NBC 2016, IS codes, NFPA standards.

STEP 03

Findings report

Prioritised, with photos and code references.

STEP 04

Handover meeting

What to push back on the builder, what to accept.

This is a pattern, not an outlier.

§ Selected audits
Project A · Q4 2022

Multi-tower mid-to-high-rise

51 findings
51 critical
4 trades audited
Project B · Q4 2022

High-rise gated community

102 findings
49 critical 1 medium
5 trades audited
Project C · Q3 2025

Multi-tower residential complex

80 findings
78 critical 2 medium
4 trades audited
Project D · Q3 2025

Multi-tower residential community

47 findings
46 critical 1 medium
4 trades audited
Project E · Q1 2026

Multi-tower high-rise complex

65 findings
47 critical 18 medium
4 trades audited
Project F · Q1 2026

Multi-tower high-rise (9+ towers)

92 findings
47 critical 45 medium
5 trades audited
Project G · Q4 2024

Multi-tower residential community (5 towers)

47 findings
25 critical 10 medium
6 trades audited
Project H · Q3 2025

Four residential towers + clubhouse

33 findings
33 critical
4 trades audited

Don’t take possession blind.

We’ve audited every kind of building on this page. Tell us about yours.

Or talk to us first — 080‑26639780