Handover audit findings
What our engineers found at various handovers
Lifts, fire-fighting, sewage treatment plants and diesel generators: four reports counted from our engineers’ own written observations, from the handover audits residents’ associations have commissioned from us since 2017. No building, builder or association is named.
The four reports
Four systems residents assume are ready on day one
Each report is four pages: the headline numbers, the patterns behind them, the checks that failed most often, and how the counting was done.
Lifts
Lift safety and function
Worst failure rateA statutory operating licence, displayed where residents can see it: failed 69 of 115 times.
- Earthing and wiring was the largest pattern (272 findings).
- An intercom that lets someone shut in the car reach a person failed 28 of 68 times.
Fire-fighting
Sprinklers, hydrants, alarms and extinguishers
Most widespreadNo fire extinguisher where one was required: found in 33 of 43 projects.
- Protective caps still on sprinkler heads in 28 of 43 projects.
- No key or means of opening a hose cabinet or fire-shaft door in 22 of 43.
Sewage treatment plant
The STP, its pumps and its operators
Most seriousRaw sewage or sludge sent out of the premises without treatment: recorded in 9 projects.
- Plant run in manual, not automatic, mode in 14 of 18 projects asked.
- No first-aid kit inside the plant in 19 of 22 projects asked.
Diesel generator (DG) set
The DG set, its fuel and its wiring
Most widespreadEarthing not done, not connected or not done properly: found in 31 of 37 projects.
- Oil, diesel or fuel leaking or spilt in 25 of 37 projects.
- Statutory approvals not produced or not on display in 6 of 12 projects asked.
A common thread
Earthing came up in three of the four
IS 3043 is the Indian Standard code of practice for earthing, and it comes up in all three of these reports.
findings on earthing and wiring, the largest lift pattern, in 10 of 12 projects
projects with earthing missing, not connected or not done to IS 3043
projects with earthing not done, not connected or not done properly
How to read these numbers
What the reports do not say
Found so they would be fixed
A handover audit gives the association a list to hand back to the builder before it accepts the building. Nothing here is the current condition of any building.
No one is named
No building, builder or residents’ association is identified, in the reports or on this page.
Not a random sample
Every project here had an association organised enough to commission an independent audit, which may make it better managed than average, not worse.
Counts, not estimates
Every figure is a count of records written down on site. Severity is the engineer’s call on site. Each report sets out exactly how it counted.
Please note: We work for both associations and developers. Where we already hold a quality-assurance engagement with the developer of your building, we will tell you before we quote.
Taking over from your builder?
Get the same list for your own building
Talk to an engineer about your society’s handover: scope, timeline and what the audit would cover.